Well we got the partial approval on the footers about a week ago,
somewhere around April 12, 2006. It was partial because the
footers weren't able to be completed because of two cribbing stacks
supporting the house. I think I mentioned that in the last
article.
The mason showed up Monday morning and when I got there around 10am
they had the bottom half of the back wall done and two other
corners! I was impressed.


Jeff, my mason, insisted things would slow down when they started the
higher scaffolding work. I still don't believe it, I think he'll
be well within the 7-10 days he estimated, of course he can't do the
full walls because the support beams are in the way.

I'll snap some more shots today and see how we're doing. The next
part of this choreography will be to get my beams set in place as the
mover takes his out. I also need to get the sill plate attached,
but that has to be done in sections as well.
A bit of head scratching to do.